Closing a completed Project on Project Server This is bit a process, so bear with
me on the lengthy Post. Before we can start the Archiving of completed
projects, there is a bit of work to be done, on existing projects. This will
have to be done, otherwise the process will not work.
First Things First :
This post requires a new custom field to be created on Project Level using a lookup table with
" Registered, In Progress and Completed" as values.
Once the field and lookup has been created follow the steps below.
Please do
the following for ALL Projects on the PWA environment. Navigate to
Project Center and click on a Projects Name :
This will
then open the Project Basic Info PdP (Assuming no customization has been done) if there was customization done on the PDP's the field needs to be added to the relevant PDP
Figure 2: Set relevant Project Status |
You will
notice a new field at the Bottom labelled “Project Status” For EVERY
project the correct value needs to be selected, either, Registered, In Progress
or Completed. If this has not been done for all projects the rest of the
process becomes Null and Void.
To correctly archive projects please follow these steps :
1. Open Project Schedule in Microsoft
Project
2. Insert the remaining work column
into the current view.
3. Remove ALL remaining work on
the schedule for all tasks (so there must be Zero remaining work on all tasks)
4. Change to the Resource Sheet
view and Insert the “Booking Type” column
a.
Change
the Booking type for all resources to Proposed (This will “release” resource
allocations to the schedule)
5. Change to the Gantt Chart
view – and Insert the “Published” column
a.
Change
the value of all tasks (Summery Tasks will not change) in the Published column
to “No” (This will un-publish all tasks from resources Timesheets)
6. Open the “Project Information”
Dialog Box from the “Project Tab” on the ribbon.
a.
Change
the Project Status field to “Completed” – Click Ok
7. Save and Publish project as per
normal.
If you now
navigate to the Project Center and have a look on the ribbon, there are
2 new Views:
Create 2 new views (or 1 new view for the archived / completed projects) You can always edit your existing (All Projects View or Summery view) to show only In Progress and Registered by filtering out "Completed" projects.
Add the "Archive / Completed view and filter out both, In Progress and Registered Projects. (If your security is setup in such a way, you can make this Archive view available to a certain category only like the PMO.
Below is an example of 2 views that has been created.
·
*All
Completed Projects (This will show all Projects that have been completed)
·
*All
In-Progress Projects (This will show all Projects with the status of
“Registered or “In Progress”) Completed Projects will not be displayed in this
view.
Figure 3 : New views |
trust this well help with the process. If you have questions please drop me a comment on the post.